A new, $39 million replacement secondary school built to LEED Gold standards, with capacity for 900 students. Green design features include the use of wood from sustainable forest practices, a ground source heat exchange system, storm water management, automatic controls for heating, cooling and ventilation, and enhanced use of natural lighting.
Duchess Park Secondary School Project
Project Description
Project Status:
Completed May 2010
Client:
School District No. 57
Project Cost:
$39 million
Partner:
Western Industrial Contractors Ltd.
Project Milestones
Request for Qualifications Issued
December 14, 2007
Request for Qualifications Closed
January 21, 2008
Shortlist Announced
January 29, 2008
Request for Proposals Issued
February 28, 2008
Contract Award
May 26, 2008
Construction Began
May 30, 2008
Construction Completed
May 10, 2010