The John Hart Generating Station Replacement Project, located in Campbell River, involved the replacement of the existing six-unit, 126 MW generating station. Project benefits included improved seismic safety, protecting fisheries resources, along with increased power capacity and reliability.
- News Release: BC Hydro signs major contract for John Hart project (February 28, 2014)
- News Release: John Hart project business event announced (February 26, 2014)
- John Hart project update email notice: preferred contractor announced (November 12, 2013)
- John Hart site plan and profile (November 12, 2013)
- News Release: B.C. Utilities Commission approves John Hart generating station replacement (February 8, 2013)
- Information Bulletin: Companies shortlisted to build new John Hart generating station (July 6, 2012)
- News Release: John Hart Project brings jobs and reliable electricity to Vancouver Island (March 13, 2012)