Surrey Langley SkyTrain Project (SLS Project)

Project Description

The Surrey Langley SkyTrain Project (SLS Project) is a 16-km elevated extension of the existing Expo Line primarily along Fraser Highway from the current terminus at King George Station in the City of Surrey, through the Township of Langley to a new terminus station at 203 St. in Langley City Centre. The Project includes eight new stations, three new transit exchanges, and nine new propulsion power substations.

The SLS Project consists of the following separately procured and staggered contracts:

  1. Guideway Contract – including substructures, superstructures, roadworks, and utilities, procured under a Design-Build-Finance (DBF) model.
  2. Stations Contract – including eight passenger stations, nine propulsion power substations, and 250m of guideway construction at the terminus station, procured under a Design-Build (DB) model.
  3. Systems and Trackwork Contract – including trackwork, power rail and linear induction motor (LIM) rail system, communications, automated train control, and power propulsion equipment, procured under a Target Price model.

Project Status:

Under Construction

Client:

Ministry of Transportation and Transit

Project Delivered By:

Transportation Investment Corporation

Project Cost:

$5.996 billion (Total cost of the Surrey Langley SkyTrain)

Project Milestones

Guideway Contract — Request for Qualifications issued
August 2, 2022
Guideway Contract — Request for Qualifications closed
November 1, 2022
Guideway Contract — Announce shortlisted respondents
January 3, 2023
Guideway Contract — Request for Proposals issued
January 3, 2023
Guideway Contract — Request for Proposals closed
December 1, 2023
Guideway Contract — Contract award
2024
Guideway Contract — Construction began
2024
Guideway Contract — Construction complete
2029 (anticipated)
Stations Contract — Request for Qualifications issued
October 3, 2022
Stations Contract — Request for Qualifications closed
January 5, 2023
Stations Contract — Announce shortlisted respondents
March 27, 2023
Stations Contract — Request for Proposals issued
March 27, 2023
Stations Contract — Request for Proposals closed
December 1, 2023
Stations Contract — Contract award
2024
Stations Contract — Construction began
2024
Stations Contract — Construction complete
2029 (anticipated)
Systems and Trackwork — Contract Request for Qualifications issued
November 14, 2022
Systems and Trackwork — Request for Qualifications closed
January 23, 2023
Systems and Trackwork — Announce shortlisted respondents
April 25, 2023
Systems and Trackwork — Request for Proposals issued
April 25, 2023
Systems and Trackwork — Request for Proposals closed
January 12, 2024
Systems and Trackwork — Contract award
2024
Systems and Trackwork — Construction began
2024
Systems and Trackwork — Construction complete
2029 (anticipated)

Project Contacts

Brie Hemingway
Project Director
Brie.Hemingway@infrastructurebc.com

Jordan Royer
Senior Associate
Jordan.Royer@infrastructurebc.com