Kicking Horse Canyon Project – Phase 4
The Kicking Horse Canyon Project is a multi-phase project to improve safety and mobility over approximately 26 kilometres of two-lane highway.
Kicking Horse Canyon Project – Phase 4
Project Details
The Kicking Horse Canyon Project is a multi-phase project to improve safety and mobility over approximately 26 kilometres of two-lane highway. Three phases of work have been completed. The fourth and final phase to transform the remaining section of about 4.8 kilometres, is being prepared for a construction start in 2020. By the end of 2023-24, this section will also feature four lanes of divided highway, along with improved avalanche and rock fall protection, fencing and passage for wildlife, and wider shoulders to accommodate cyclists.
Client: | Ministry of Transportation and Infrastructure |
Project delivered by: | Transportation Investment Corporation |
Project Cost: | $601 million |
Project Report: | IBC_KickingHorseCanyonPhase4ProjectReport |
Project Status: | Under construction |
Project Website: | https://www.kickinghorsecanyon.ca/ |
Project Image: | click to download |
Milestones
Request for Qualifications issued | September 5, 2019 |
Request for Qualifications closed | October 16, 2019 |
Request for Proposals issued | December 13, 2019 |
Contract award | November 6, 2020 |
Construction to begin | Summer 2020 |
Construction completed | Anticipated winter 2023-24 |
Project Updates
- Fall closures scheduled on Highway 1 for Kicking Horse Canyon construction – September 13, 2022
- Major progress on Kicking Horse Canyon Project in first year of construction – June 8, 2022
- Highway 1 closed east of Golden between Easter, Victoria Day weekends – April 5, 2022
- Major construction gets underway on Kicking Horse Canyon Phase 4
- Kicking Horse Canyon project takes key procurement step
Procurement Documents
- Kicking-Horse-Canyon-Project-Final-report-of-the-Fairness-Reviewer-RFP-process
- Kicking-Horse-Canyon-Project-Report-of-the-Fairness-Reviewer-on-the-RFQ-process
- Design-Build Agreement – (Issued November 6, 2020)
- Kicking-Horse-Canyon-Project RFP Conformed (December 13, 2019)
- Kicking-Horse-Canyon-Project Request for Qualifications (September 19, 2019) Conformed FINAL
Project Map
Project Contacts
- Email: Contact.KHCP4@gov.bc.ca