Trans-Canada – R.W. Bruhn Bridge and Approaches Project
The Highway 1 four-laning project includes approximately 1.9 km of Highway 1 four-laning, replacement of the existing R.W. Bruhn Bridge.
Trans-Canada – R.W. Bruhn Bridge and Approaches Project
Project Description
The Highway 1 four-laning project includes approximately 1.9 km of Highway 1 four-laning, replacement of the existing R.W. Bruhn Bridge with a new four-lane bridge, and intersection improvements between Old Sicamous Road and Silver Sands Road.
Client: | Ministry of Transportation and Infrastructure |
Project Cost: | $224M (estimated) |
Partner: | TBD |
Project Status: | In procurement |
Project Website: | gov.bc.ca/gov/content/transportation-projects/highway1-kamloops-alberta/rw-bruhn-bridge |
Milestones
Request for Qualifications Issued | December 8, 2023 |
Request for Qualifications Closed | January 18, 2024 |
Contract Award | May 2024 (anticipated) |
Project Completion | Summer 2027 (anticipated) |
Project Updates
- March 2024 – The project has moved to tender phase overseen by the Province, through the Ministry of Transportation and Infrastructure
- Bruhn Bridge replacement project takes another step forward – December 12, 2023